Laboratory Setup Cost: A Budget Planning Guide for 2027

Laboratory setup 6 min read

The cost of setting up a laboratory cannot be worked out from a price per square metre; it is the sum of design, building work, ventilation, electrical, gas and plumbing services, flooring, laboratory furniture, fume hoods, chemical storage, safety equipment and testing. The number of fume hoods, the existing building, the worktops, any cleanroom and the scope of work move the budget most. An accurate budget is drawn up item by item once the requirements and layout are ready.

Managers preparing a budget for a laboratory usually start by asking for a price per square metre. Yet if one of two laboratories of the same size has six fume hoods and extensive gas services and the other only instrumental analysis benches, their costs will be very different. This article sets out the items that make up the cost, the decisions that move the budget most and how to draw up a budget for your 2027 investment step by step. We give no figures: an accurate figure can only be worked out from your requirements and your space.

The 12 Items Behind the Cost

ItemScopeWhat sets the cost
1. DesignArchitectural, mechanical, electrical, gas and furniture designs, 3D layoutSize of the laboratory and scope of design
2. Building and interior worksPartitions, suspended ceilings, paint, doorsChanges needed in the existing building
3. VentilationExhaust ducts, fans, fresh airNumber of fume hoods and extraction arms, duct route
4. ElectricalDistribution boards, lighting and emergency lighting, UPS, earthing, low-current systemsPower of the instruments and need for uninterrupted supply
5. GasGas lines, outlets, gas cylinder cabinetsTypes of gas and number of outlets
6. PlumbingWater and waste water lines, sinksNumber of sinks and water points
7. FlooringChemical-resistant floorArea and chemicals in use
8. Laboratory furnitureWall and island benches, base and wall cabinets, service unitsBench length, frame system, worktop material
9. Fume hoods and local extractionFume hoods, canopy hoods, extraction armsType, size and number
10. Chemical and gas storageFire-resistant chemical storage and gas cylinder cabinetsQuantity and class of chemicals stored
11. Safety equipmentEmergency showers and eyewash, fire detectionType of laboratory and risk assessment
12. Testing, training and handoverFume hood airflow tests, calibration, user trainingAmount of equipment; ISO 14644-1 verification if there is a cleanroom

The analytical instruments themselves may be budgeted separately, depending on the scope of the quotation. The instrument list is still needed first: the size, weight and electrical, gas and water needs of the instruments directly change most of the items above.

The 5 Decisions That Move the Budget Most

  1. Number of fume hoods and ventilation: Each fume hood brings an exhaust duct, a fan and a need for fresh air. The fan and duct are calculated from the size of the hood and the route of the duct, so the number of fume hoods should be settled by the risk assessment at the layout stage. See what sets the price of a fume hood.
  2. Existing or new building: In an existing building, the ceiling height, the route for the exhaust duct to the outside, the electrical capacity and the water and waste water points decide the alterations needed. A constraint missed at the survey comes back on site as cost and time.
  3. Worktops: Not every section needs the most expensive surface; each section needs a surface that stands up to its chemicals. We explain the factors in what sets the price of laboratory benches.
  4. Cleanroom: If microbiology or sterile production areas call for a cleanroom, panels, filtration, airflow and class verification are added as separate items. See our cleanroom installation page for the scope.
  5. Scope of work: When design, services, furniture and installation go to different companies, the client has to coordinate them and gaps between the items can surface later as extra work. In a turnkey laboratory this work is run by one company on one programme.

6 Steps to a 2027 Budget

  1. Write the requirements: The analyses to be carried out, the instrument list (with size, weight and electrical, gas and water needs), the chemicals to be used and the number of people who will work there.
  2. Have the space surveyed: The survey records dimensions, ceiling height, exhaust route, electrical capacity and water and waste water points.
  3. Approve the layout: Benches, fume hoods and instruments are laid out in three dimensions. Our planning software derives from the layout the list and quantities of all the parts needed to complete the laboratory, and the furniture items are priced from that list.
  4. Price item by item: The 12 items above are priced separately and what is in the scope is set out in writing.
  5. Split into phases if needed: If the budget does not cover everything at once, priority sections are chosen. Planning the ventilation, electrical and gas services for the whole laboratory in the first phase avoids reopening them later, and new modules can be added to modular benches.
  6. Prepare the documents: For public institutions and universities, the layout and the itemised list form the basis of the technical specification and the cost estimate. The programme is drawn up with the critical path method (CPM).

See how to set up a laboratory for how these steps work in practice and laboratory planning and consultancy for the scope of design.

An Example: Design First, Then the Investment Decision

For the Sunar Mısır Quality-Control Laboratory Building, the internal circulation was reworked without touching the building’s main structure, and every space from the offices and the sample and chemical storage rooms to the main laboratory was designed together with the electrical, plumbing and ventilation infrastructure. With its architectural and technical design complete, the project is at the investment-planning stage. It shows how a budget can rest on a finished design rather than an estimate.

Questions to Ask When Comparing Quotations

  • Are the design drawings, tests and user training in the scope?
  • Does the fume hood quotation include the fan, duct and airflow test?
  • Are the worktop material and thickness the same; are cabinets, sinks and service units included?
  • Who carries out delivery, installation and service connections?
  • Are the programme and handover date in writing?

Frequently Asked Questions

What does a laboratory cost per square metre?
A price per square metre gives only a rough idea. As the number of fume hoods, ventilation, services and worktops change, two laboratories of the same size can differ markedly in cost. That is why we publish no price list and prepare an itemised quotation from the requirements and layout.
Where can a laboratory budget be saved?
Choosing a worktop suited to each section's chemicals, setting the number of fume hoods by risk assessment and listing the instruments at the start so that services are not reopened later all protect the budget. Safety items such as ventilation, chemical storage and emergency showers should not be cut.
Can a laboratory be set up in phases?
Yes. Priority sections are set up first. If the services are planned for the whole laboratory from the start, later phases can be added without reopening them.
What information is needed to work out the cost?
The analyses to be carried out, the instrument list, the chemicals to be used, the number of users, the plan of the space and details of the existing services. Public institutions should add any technical specification or tender documents.
Are the analytical instruments included in the setup cost?
It depends on the scope of the quotation. Even if instruments are budgeted separately, the instrument list is needed first, because the electrical, gas, water and ventilation items are calculated from it.
Preparing a laboratory budget for 2027? Send us your requirements and the plan of the space; we will settle the layout and items with you and prepare an itemised quotation. Ask for a survey and quotation · Turnkey laboratories

More Articles

All Articles
  • Laboratory benches

    C-Frame, H-Frame and Plinth Benches: Differences and How to Choose

    C-frame, H-frame and plinth laboratory benches differ in what carries the worktop and the instruments on it. On a C-frame a steel structure carries the load and the base cabinets are suspended or mobile; on an H-frame legs bolted on site carry it and the cabinets are mobile; on a plinth bench the base cabinets carry it. Instrument weight, density of services, cleaning and whether the layout may change decide the choice.

  • Laboratory benches

    What Sets the Price of Laboratory Benches? Frame, Worktop and Equipment

    The price of laboratory benches depends on the frame system (C-frame, H-frame or plinth), whether they are wall or island benches, their dimensions, the worktop material, base and wall cabinets, sinks and fittings, service units and the scope of installation. A single price per metre can therefore mislead; the right price comes from the layout and the chemicals to be used.

  • Laboratory setup

    How to Set Up a Laboratory: 7 Steps from Design to Handover

    A laboratory is set up in seven steps: needs and workflow analysis, site and infrastructure survey, layout design, technical designs, manufacturing and supply, services and installation, and finally testing, training and handover. The duration and cost depend on the size of the laboratory, the chemicals used, the ventilation required and the infrastructure of the existing building.